An online map can identify a likely path. A builder can offer an early opinion. Neither proves that a particular ADU fits the property. A useful feasibility check coordinates the rules with the physical lot and leaves a written record that can follow the project to another designer or builder.

Start with the parcel and the proposed dwelling
Confirm the legal parcel and whether it sits inside Austin, another city or an unincorporated area. Record the county, zoning, subdivision, utility companies and any planned development or deed restrictions. A postal address is not enough.
Then describe the project in plain terms:
- how many homes exist now and how many are proposed;
- whether the new dwelling is detached, attached, internal or a garage conversion;
- which building stays or changes;
- the rough living area and number of bedrooms;
- how residents reach the entrance; and
- whether any subdivision or small-lot work is proposed.
Inside Austin, the answer may use the City’s ADU guidance, a HOME Phase 1 two-unit or three-unit path, or the HOME Phase 2 small-lot path. Zoning is only one part of the review. Building, floodplain, trees, historic, septic and other groups may become relevant based on the property and proposal. The HOME and ADU guide explains the main choices.
Draw the usable part of the lot
Gather the latest survey, recorded plat, current plans, easements and available permit history. Draw one base plan at a useful scale. Label the source and date of every important dimension.
Show:
- property boundaries and existing buildings;
- roofs, porches, walks, driveways and other hard surfaces;
- easements and likely service corridors;
- tree trunks, canopies and the area around roots;
- grade, drainage paths, flood information and nearby creeks;
- parking and ordinary resident access;
- construction access and staging; and
- at least one proposed ADU location.
The space that appears open in the backyard is not automatically the usable building area. The drawing should make conflicts visible before design time is spent solving the wrong problem.
Investigate Austin trees, flood and drainage conditions
Austin regulates protected trees from 19 inches in diameter and qualifying heritage species from 24 inches. Species, measurement and the planned work determine the actual review. Mark every significant tree near the footprint, foundation, trench or construction path. If those areas overlap, obtain the right professional advice early.
Residential review also identifies floodplain and creek-related triggers. Property in or within 100 feet of the 100-year floodplain can require floodplain review. Some land close to a creek can require an erosion-hazard assessment. Grading and new hard surfaces can also change how rain crosses the lot.
Do not treat these facts as reasons the project must fail. Treat them as placement and scope questions. A smaller footprint, different location, adjusted foundation or revised utility route may produce a better project, but only after the evidence is clear.
Trace access and utilities before pricing
Mark the current electric service and panel, water meter or service, wastewater connection or septic system, gas if relevant and likely mechanical-equipment locations. Draw a possible route from each service to the ADU.
Austin Water publishes different paths for a new meter, a tap plan and an upgrade to an existing meter. The property’s provider, service capacity and proposed connection determine which route applies. Electricity may need a load calculation, meter planning or service changes. Wastewater depth and distance can affect whether the preferred footprint is practical.
Also draw the contractor’s route. Note fence openings, side-yard width, overhead lines, trees, paving and landscape that equipment or materials would cross. A floor plan price can miss trenching, restricted access and repairs outside the dwelling.
Use the utilities and site-work guide to turn these items into quote lines.
Put the address and reviews on the schedule
Austin requires a unique address or building number for each new dwelling before the residential permit application. Assign that task to a person and record when it must happen.
Create a short review register with four columns:
| Question | Evidence needed | Responsible person | Effect if unresolved |
|---|---|---|---|
| Which housing path applies? | Current City rule and parcel record | Owner or designer | Wrong plans or unit count |
| Where can the ADU fit? | Survey and site findings | Surveyor/designer | Redesign or lost area |
| How will services connect? | Provider records and early calculations | Designer/trades | Upgrade or trench cost |
| Which specialist review applies? | Authority or consultant answer | Project lead | Added documents or time |
This keeps a likely answer from silently becoming an assumption.
Finish with a clear feasibility outcome
A useful review ends with one of four conclusions:
- Proceed: the main path and next design stage have reasonable support.
- Proceed after a named check: one or more pieces of evidence are needed first.
- Revise: another size, location or dwelling arrangement is more credible.
- Stop this concept: a controlling constraint or budget mismatch makes the current idea unsuitable.
For every open item, record who will answer it, what they will deliver and what changes if the answer is unfavorable. Avoid reports that offer only “research” or “concept design” without a property plan and a list of unresolved decisions.
Send every builder the same feasibility brief
Once the main facts are assembled, give each bidder the same package:
- address and jurisdiction;
- intended dwelling arrangement and rough size;
- base plan or survey;
- known tree, drainage, access and utility conditions;
- selected housing or permit path, if confirmed;
- services expected from the bidder;
- budget position and timing; and
- remaining questions.
That is enough to start a useful conversation without pretending the project is permit-ready. The cost guide helps you compare the whole project, while the quote form provides one direct next step.
Frequently asked questions
Does an online zoning map prove that an ADU is allowed?
No. It can identify a likely starting point. Austin review can also involve site, building, tree, floodplain, historic, septic and other property-specific questions.
When do Austin trees affect an ADU plan?
Austin tree guidance starts with protected trees from 19 inches in diameter and qualifying heritage species from 24 inches. The species, measurement and proposed work determine what review is required.
Does a new Austin ADU need its own address?
Yes. Austin says each new dwelling needs a unique address or building number before the residential permit application is submitted.
Can I price utilities without checking the existing service?
Only as an explicit allowance. The provider, existing capacity, connection points, meter route and trench conditions determine the real scope.